Operating Manual
31
© Copyright 2016
OMBG3000 – Rev1
Installation
4
4.1
Pre-Installation Requirements
General
4.1.1
It is LANDTEC’s recommendation that the installation of the BIOGAS 3000 is
carried out in accordance with this operating manual and the latest edition of
IEC 60079-14. Any electrical work should be carried out by a competent
electrician and any relevant codes of practice should be followed.
In order to effectively install the BIOGAS 3000 system it is important that the
site is ready and in a fit state. In particular, the following points should be
noted:
Warning
Power should NOT be applied before all piping and
wiring has been completed and tested.
Only a qualified person should make electrical
connections to the system.
This operating manual has been read and fully understood
A risk assessment has been performed that includes installation,
operation, and maintenance of the system and the removal, where
practicably possible, of any identified hazards
Applicable codes of practice identified
The BIOGAS 3000 system has been received on site, unpacked,
packaging contents checked, and checked for obvious damage
A suitable location is determined for the installation of the
instrumentation
Note: Refer to section
considered.
A suitable mains supply as detailed in this manual is installed
All required gas lines are installed