Model 4500 Premier Dust and Opacity Monitor
21
A3-8 Mounting the Transceiver and Retro-Reflector
1
Ideally the instrument should be installed when the process is not operating and the stack is
cold.
2
The air blower unit should operating and connected to the Transceiver and Retro-Reflector
before
the instrument is mounted on to the flanges.
3
Check that each mounting stud has six pairs of spring washers (5) arranged as shown - these
may have been removed if the flange alignment tool was used.
4
Place a rubber sealing band over the mounting flanges for the Transceiver and Retro-Reflector.
It cannot be fitted after the instrument is mounted on the flange.
5
Remove the three M12 nuts (4) and dome washers (7) from the mounting flange (1), and
locate the Transceiver (2) on to the studs (3).
6
Replace the Nyloc nuts (4) and dome washers (7) and tighten them, compressing the spring
washers (5), until there is a gap of 13 mm (½”) between the two flanges (1 and 2), all round.
Pull the sealing band (6) into place over the gap.
6
Install the Retro-Reflector following the same procedure.
sealing band
1
2
3
4
5
6
13 (½")
7
mounting
flange
transceiver
Summary of Contents for 4500 MKII Premier
Page 2: ......
Page 4: ......
Page 10: ......
Page 28: ...Model 4500 Premier Dust and Opacity Monitor 28...
Page 135: ...Model 4500 Premier Dust Opacity Monitor Appendix Part No 770 084...
Page 136: ......