4.3.1
Special Tools
No special tools are required for the installation, maintenance or repair of this machine.
LMFC250 FINE CRUSHER MANUAL
4.3.2
Installation Procedure
The correct installation procedure for the LMFC 250 Crusher, being bolted to a concrete floor, is as follows:
•
Ensure all site services are correctly measured and placed aside, ready for installation. (i.e. correct cable length).
•
Correct measurement and placement of the mounting holes is essential. It is advisable to place the Crusher in position
and use the fixing holes in the base frame as a template.
•
Drill the required number of holes into the floor to secure the Crusher, suitable for appropriate size.
•
Lower the Crusher into place using a forklift and the eye bolts and take care to accurately position the machine. Secure
the machine to the floor/platform.
4.3.3
Assembly Instructions
The machine is supplied as a complete unit, no assembly is required.
The machine comes as a complete unit, so no additional parts requiring installation will be included, unless specifically
requested, such as optional extras. Ensure the standard issue of items indicated in Section 3 (Checklist of Supplied Parts)
have been received.
4.3
Installation of Equipment
4.4.1
Pre
-
Operation
Prior to starting the Crusher, perform the following checks
•
Perform a visual check on the machine to check for any damaged or broken parts.
•
Check that all electrical connections have been made correctly.
•
Ensure the dust extraction system has been installed correctly.
•
Check that the hopper and jaw throat are clear of any material or objects that might damage the jaws.
•
Ensure that the particle size adjustment lock bolt (46 mm) on the back of the pitman housing is secure with the lock nut.
•
Remove the V belt cover and check the drive belt adjustment.
•
Remove the flywheel cover and rotate the flywheel by hand to ensure the jaw plates do not touch and jam and that the
flywheel freely turns whole revolutions.
•
Check that the Crusher is seated correctly on its mounting.
4.4.2
Operation of the Crusher
To manually dry commission the Crusher, follow the procedure outlined below.
•
Start and stop the Crusher.
•
Run the Crusher without any material for approximately two (2) hours. During this test run check the temperature of the side
plates of the machine.
Following is the procedure for dry commissioning the LMFC 250 Crusher. Follow these instructions to carefully operate and
to test the Crusher.
4.4
Dry Commissioning
5
19