The operating personnel is required to inspect the chipper at least once daily and
report any defects or changes in operation immediately.
2.13
Regular inspection, maintenance and repair checks must only be performed with ma-
chine at a standstill.
If for this purpose protecting devices, coverings or similar have to be opened or re-
moved, the drum chipper must be prevented from accidental starting. This is normally
done by locking out the main switch.
2.14
Any work must only be performed with machine at a standstill.
2.15
No protective or safety devices may be removed.
If it is necessary to remove guards for maintenance, they must be re-installed imme-
diately upon completion of the work.
2.16
The hydraulic unit is equipped with an accumulator. This may have to be inspected
and approved by the local authorities. The user is responsible to observe the local
regulations in full and obtain such approval if necessary as well as later re-
inspections.
2.17
The accumulator was sealed through TÜV, the appropriate authority in Germany and
the seal may not be removed.
2.18
All work on the hydraulic unit, except as listed here-in, must only be performed by
qualified tradesmen.
2.19
Prior to any work on any part of the hydraulics, all machine parts must be lowered.
2.20
Those units in connection with the accumulator will remain pressurised after lowering
of machine parts and motors are stopped. For this reason, the oilside of the accumu-
lator must be drained prior to commencing work on the hydraulics. (see chapter „in-