START-UP
After completing the installation and all electrical work, start up procedure is to
be executed as follows:
6.1
Preliminary checks
•
During shipment the rotor was secured against rotation by means of the
holding pin. This pin can now be removed.
•
Check all bolts for proper tightness. The knife clamping bolts (or spindle
for wedge type clamping) must be checked with torque wrench supplied
with the chipper (see „operating instructions“).
•
Check rotor space, chipper inlet and feedroll area for foreign objects
such as tools, hard hats, welding rods etc.
•
Check electrical installation in accordance with all local rules and regula-
tions.
•
Check rotation of all E-motors.
•
Check oil and gas pressure in accumulator (see chapter „Inspection and
Maintenance“).
•
Bleed hydraulic system by carefully loosening the topmost fitting on the
cylinders until oil appears.
•
Check lowering speed of top feedroll carrier. This can be adjusted with
the flow control in the cylinder connection or throttle valve (see „Spare
part drawings and piece lists / assembly hydraulic plant“).