44 / 61
Carrying out emptying
2019/11
010-917_SON_EN
Carrying out emptying in automatic operation
(The steps carried out in automatic operation can be actuated individually via manual operation)
• Switch the control unit on.
• Set up the hose connection between the emptying vehicle and the direct disposal pipe.
• Press the key
Start / Stop
, the menu
Maintenance
appears.
•
Select
Automatic operation
and press OK, the menu
Automatic operation
appears.
•
Select
Start automatic operation
the emptying workflow <A1> is activated. The functions pump operating
times, hot water supply and the valve switchover are carried out automatically Abb. [40].
Every program step can be skipped by setting the reference time to 0.
The times must be optimised according to pumping height, temperature and water pressure. Flow through
solenoid valve DN 25 at 1 l/sec., in the case of deviated inflow rates the filling times must be adapted in the
control unit. (see Operating menu on page 50) =>menu 3.1.1 to 3.1.13 can be set)
• Remove the hose connection to the emptying vehicle.
If the system tank is not filled with water again after emptying (upper edge outlet assembly lower section),
greases and suspended matter can flow freely into the sewage system.
•
Switch the control unit off if appropriate.