JOHNSON CONTROLS
66
FORM 150.62-NM6 (103)
JOb NAME: ______________________________
SALES ORDER #: _________________________
LOCATION: ______________________________
SOLD bY: ________________________________
INSTALLING
CONTRACTOR: ___________________________
START-UP
TECHNICIAN/
COMPANY: _______________________________
START-UP DATE : _________________________
CHILLER MODEL #: _______________________
SERIAL #: ______________________________
__
CHECKING THE SYSTEM
PRIOR TO INITIAL START (NO POwER)
Unit Checks
1. Inspect the unit for shipping or installation dam-
age.
2. Assure that all piping has been completed.
3. Visually check for refrigerant piping leaks.
4. Open suction line ball valve, discharge line ball
valve, and liquid line valve for each system.
5. The compressor oil level should be maintained so
that an oil level is visible in the sight glass. The
oil level can only be tested when the compressor
is running in stabilized conditions, guaranteeing
that there is no liquid refrigerant in the lower shell
of the compressor. In this case, the oil should be
between 1/4 and 3/4 in the sight glass. At shut-
down, the oil level can fall to the bottom limit of
the oil sight glass.
6. Assure water pumps are on. Check and adjust
water pump flow rate and pressure drop across
the cooler (see LIMITATIONS). Verify flow switch
operation.
Excessive flow may cause catastrophic
damage to the evaporator.
7. Check the control panel to ensure it is free of
foreign material (wires, metal chips, etc.).
PRE-STARTUP CHECKLIST
8. Visually inspect wiring (power and control). Wiring
MUST meet N.E.C. and local codes. See Figures
2- 5, pages 14 - 17.
9. Check tightness of power wiring inside the power
panel on both sides of the motor contactors and
overloads.
10. Check for proper size fuses in main and control
circuits, and verify overload setting corresponds
with RLA and FLA values in electrical tables.
11. Assure 120VAC Control Power to CTb2 has 15
amp minimum capacity. See Table 1, page 20.
12. be certain all water temp sensors are inserted
completely in their respective wells and are
coated with heat conductive compound.
13. Assure that evaporator TxV bulbs are strapped
onto the suction lines at 4 or 8 o’clock positions
or suction temp. sensors if EEVs are installed.
14. Assure oil level in the compressor or oil line sight
glasses is between 1/4 - 3/4.
15. Check the tightness of the heaters on each com-
pressor. Tighten the heater if the heater fingers
do not touch the compressor housing. Inspect
the heater around the entire perimeter of each
compressor. The heater should be torqued to 26
in./lbs., ± 4 in./lbs.
COMPRESSOR HEATERS
(POwER ON – 24 HOURS PRIOR TO START)
1. Apply 120VAC and verify its value between ter-
minals 5 and 2 of CTb2. The voltage should be
/- 10%.
Power must be applied 24 hours prior to
start-up.
Each heater should draw approximately 0.5-1A.
PANEL CHECKS
(POwER ON – bOTH UNIT SwITCH OFF)
1. Apply 3-phase power and verify its value. Volt-
age imbalance should be no more than 2% of the
average voltage.
2. Apply 120VAC and verify its value on the terminal
block in the Power Panel. Make the measurement
between terminals 5 and 2 of CTb2. The voltage
should be /- 10%.
3. Program/verify the Cooling Setpoints, Program
Setpoints, and unit Options. Record the values
below (see sections on Setpoints and Unit Keys
for programming instruction).
Installation
Summary of Contents for York YCAL0014E Series
Page 111: ...JOHNSON CONTROLS 111 FORM 150 62 nm6 103 2 This page intentionally left blank...
Page 133: ...JOHNSON CONTROLS 133 FORM 150 62 nm6 103 4 LD08851...
Page 135: ...JOHNSON CONTROLS 135 FORM 150 62 nm6 103 4 This page intentionally left blank...
Page 137: ...JOHNSON CONTROLS 137 FORM 150 62 nm6 103 LD08855 4...
Page 139: ...JOHNSON CONTROLS 139 FORM 150 62 nm6 103 4 This page intentionally left blank...
Page 141: ...JOHNSON CONTROLS 141 FORM 150 62 nm6 103 LD08858 4...
Page 143: ...JOHNSON CONTROLS 143 FORM 150 62 nm6 103 4 This page intentionally left blank...
Page 145: ...JOHNSON CONTROLS 145 FORM 150 62 nm6 103 LD08862 4...
Page 147: ...JOHNSON CONTROLS 147 FORM 150 62 nm6 103 4 This page intentionally left blank...
Page 149: ...JOHNSON CONTROLS 149 FORM 150 62 nm6 103 LD08865...
Page 151: ...JOHNSON CONTROLS 151 FORM 150 62 nm6 103 LD08867...
Page 153: ...JOHNSON CONTROLS 153 FORM 150 62 nm6 103 LD08869...
Page 155: ...JOHNSON CONTROLS 155 FORM 150 62 nm6 103 4 This page intentionally left blank...
Page 157: ...JOHNSON CONTROLS 157 FORM 150 62 nm6 103 LD08872...
Page 159: ...JOHNSON CONTROLS 159 FORM 150 62 nm6 103 4 LD08877...
Page 161: ...JOHNSON CONTROLS 161 FORM 150 62 nm6 103 LD08874...
Page 163: ...JOHNSON CONTROLS 163 FORM 150 62 nm6 103 This page intentionally left blank...
Page 165: ...JOHNSON CONTROLS 165 FORM 150 62 nm6 103 4 LD08830...
Page 167: ...JOHNSON CONTROLS 167 FORM 150 62 nm6 103 4 LD08833...
Page 169: ...JOHNSON CONTROLS 169 FORM 150 62 nm6 103 4 LD08835...
Page 171: ...JOHNSON CONTROLS 171 FORM 150 62 nm6 103 4 This page intentionally left blank...
Page 173: ...JOHNSON CONTROLS 173 FORM 150 62 nm6 103 4 LD08837...
Page 175: ...JOHNSON CONTROLS 175 FORM 150 62 nm6 103 4 LD08840...
Page 177: ...JOHNSON CONTROLS 177 FORM 150 62 nm6 103 4 LD08842...
Page 179: ...JOHNSON CONTROLS 179 FORM 150 62 nm6 103 4 This page intentionally left blank...
Page 181: ...JOHNSON CONTROLS 181 FORM 150 62 nm6 103 4 LD08844...
Page 183: ...JOHNSON CONTROLS 183 FORM 150 62 nm6 103 4 LD08847...
Page 185: ...JOHNSON CONTROLS 185 FORM 150 62 nm6 103 4 LD08849...
Page 187: ...JOHNSON CONTROLS 187 FORM 150 62 nm6 103 4 This page intentionally left blank...