U-MATCH AIR CONDITIONERS INSTALLATION
51
Sponge (gray)
Drain hose
Clamp
Clamp(attachment)
Sponge(attachment)
Below 4mm
Figure 1-1-9
2
˅
Testing of Drainage System
After the electrical installation is completed, carry out the testing of the drainage system.
During the test, check if the water correctly flows through the pipelines. Carefully observe the joints to
ensure that there is no leakage. If the unit is to be installed in a new house, carry out testing before decorating
the ceiling.
3
˅
Matters of Attention
The joint of Drainage Pipeline must not have leakage.
The Drainage Pipeline shall be installed with an inclining angel of 5
̚
10°, so as to facilitate the drainage of
condensate. The joints of the Drainage Pipeline must be covered by thermal insulation materials to avoid
generation of exterior condensate. (As shown in Figure 1-1-10)
㇑ⴆ
ߧࠍ≤㇑؍ቲ
Figure 1-1-10
1.1.7 Installation of air pipes and openings
Caution:
The air supply pipe, the air intake pipe and the fresh air pipe must be covered with a layer of thermal
insulation, so as to avoid thermal leakage and condensation. Firstly apply liquid nail on the pipes, then attach
the thermal insulation cotton with a layer of tinfoil. Use the liquid nail cover to fix it. Lastly use tinfoil
adhesive tape to carefully seal the joints; other good thermal insulation materials can also be used.
The air supply pipes and the air intake pipes shall be fixed to the prefabricated boards of the ceiling by using
Insulating layer of condensate pipe
Pipe cover
Summary of Contents for u-match on/off
Page 1: ......
Page 4: ...INVENTOR COMMERCIAL AIR CONDITION U MATCH AIR CONDITIONERS 1 PRODUCT...
Page 24: ...U MATCH AIR CONDITIONERS PRODUCT 21 5 PIPING DIAGRAM...
Page 25: ...INVENTOR COMMERCIAL AIR CONDITION U MATCH AIR CONDITIONERS 22 CONTROL...
Page 26: ...U MATCH AIR CONDITIONERS CONTROL 23 CONTROL 1 OPERATION FLOWCHART 1 1 Cooling Dry Operation...
Page 27: ...U MATCH AIR CONDITIONERS CONTROL 24 1 2 Heating Operation...
Page 45: ...U MATCH AIR CONDITIONERS CONTROL 42 5 2 4 Dimensions...
Page 48: ...INVENTOR COMMERCIAL AIR CONDITION U MATCH AIR CONDITIONERS 45 INSTALLATION...
Page 91: ...INVENTOR COMMERCIAL AIR CONDITION U MATCH AIR CONDITIONERS 88 MAINTENANCE...
Page 101: ...U MATCH AIR CONDITIONERS MAINTENANCE 98 Malfunction display E6 Communications Failure...
Page 115: ...U MATCH AIR CONDITIONERS MAINTENANCE 112...
Page 163: ......