67
6.0 Boiler operation
Before operating the appliance, there are some important pre-igntion checks that need to be
performed. For more information, see
Before operating the boiler on page 65
. To understand the
boiler start-up process, see
Sequence of Operation on page 103
6.1 Lighting and shutting down the boiler
Start-up Checklist
Check
Followed lighting and shutting down procedure.
□
Tested the ignition safety shutoff function (see
Testing the ignition safety shutoff on page
).
□
Checked the appliance's fuel source, and if necessary,
using
the appropriate P-kit.
□
Performed gas pressure test by
measuring the inlet gas pressure
□
Summary of Contents for SL 10-85 G3
Page 8: ...Intentionally left empty ...
Page 14: ...Intentionally left empty ...
Page 66: ...Figure 49 Electric wiring connections 62 Section Installation ...
Page 78: ...Intentionally left empty ...
Page 92: ...Intentionally left empty ...
Page 106: ...Internal wiring diagram Figure 53 Internal wiring diagram 102 Section Appendices ...
Page 107: ...Sequence of Operation Figure 54 Sequence of Operation 103 Sequence of Operation ...
Page 109: ...105 Exploded views of boiler parts ...
Page 114: ...110 Section Appendices ...
Page 122: ...Intentionally left empty ...