EPS 45-80 High-Voltage Generator
7-48
Technical Manual P/N 9894.00.G6
Figure 7.34
–
Replacement of EPS 45-80 Generator Basket (10/10).
Position before connecting the assembly to the Motherboard.
12.
On the generator, reinstall all screws taken out in step 4 (Figure 7.25).
13.
Reconnect all cables on the Controller board.
14.
If any, reinstall the board(s) on the Expansion Motherboard (Fluoro board, Relay board, ..).
7.6.2.3
Firmware Upload and Final Verification
When the generator is finally assembled as per the previous section instructions, it is now time to
upload the firmware in the generator.
1.
Refer to Section 7.6.5 to upload the firmware, if necessary.
2.
Take note of all firmware versions (Section 7.5.2.4):
i.
Select “System”, “Monitor” and then “Soft. Rev”.
ii.
Browse thru the firmware versions that are installed on the generator and verify they
match the table you completed before (Section 7.6.2.1).
3.
Perform the field calibration before resuming to normal operation.
Field Calibration
Refer to
X-ray Tube Calibration
Section 5.2
Fluoroscopic Entrance Exposure Rate
Section 5.4
Fluoroscopic Dose Stabilization (verification)
Section 5.5