F. Horizontal Termination Requirements
Heat Shield Requirements for Horizontal
Termination
WARNING! Risk of Fire!
To prevent overheating and
fire, heat shields must extend through the entire wall
thickness.
•
DO NOT
remove the heat shields attached to the
wall shield firestop and the horizontal termination cap
(shown in Figure 7.13).
• Heat shields must overlap 1-1/2 in. (38 mm) mini
-
mum.
There are two sections of the heat shield. One section
is factory-attached to the wall shield firestop. The other
section is factory-attached to the cap. See Figure 7.13.
If the wall thickness does not allow the required 1-1/2 in.
(38 mm) heat shield overlap when installed, an extended
heat shield must be used.
• If the wall thickness is less than 4-3/8 in./ 111 mm
(SLP), the heat shields on the cap and wall shield
firestop must be trimmed. A minimum 1-1/2 in. (38 mm)
overlap MUST be maintained.
• Use an extended heat shield if the finished wall
thickness is greater than 7-1/4 in. (184 mm).
• The extended heat shield may need to be cut to length
maintaining sufficient length for a 1-1/2 in. (38 mm)
overlap between heat shields.
• Attach the extended heat shield to either of the
existing heat shields using the screws supplied with
the extended heat shield. Refer to vent components
diagrams in the back of this manual.
• Rest the small leg on the extended heat shield on top
of the pipe section to properly space it from the pipe
section.
Figure 7.13 Venting through the wall
Note:
When using termination caps with factory-supplied
heat shield attached, no additional wall shield firestop is
required on the exterior side of a combustible wall.
Install Horizontal Termination Cap
WARNING! Risk of Fire!
The telescoping flue section of
the termination cap MUST be used when connecting vent.
• 1-1/2 (38 mm) minimum overlap of flue telescoping
section is required.
Failure to maintain overlap may cause overheating and
fire.
• Vent termination must not be recessed in the wall. Siding
may be brought to the edge of the cap base.
• Flash and seal as appropriate for siding material at
outside edges of cap.
• When installing a horizontal termination cap, follow
the cap location guidelines as prescribed by current
ANSI Z223.1
and
CAN/CGA-B149
installation codes
and refer to Section 4 of this manual.
CAUTION! Risk of Burns!
Local codes may require in-
stallation of a cap shield to prevent anything or anyone
from touching the hot cap.
NOTICE:
For certain exposures which require superior
resistance to wind-driven rain penetration, a flashing kit and
HRC caps are available. When penetrating a brick wall, a
brick extension kit is available for framing the brick.
INTERIOR
HEAT SHIELD OR
EXTENDED
HEAT SHIELD
WALL SHIELD
FIRESTOP
HEAT SHIELD
1-1/2 IN. (38 MM) MIN.
OVERLAP
SHEATHING
VENT DEPTH FROM BACK
OF APPLIANCE OUTER WRAP
TO OUTSIDE SURFACE
OF EXTERIOR WALL
(SEE CHART BELOW)
SLIP SECTION
CAN BE EXTENDED
EXTERIOR
WALL
OUTER WRAP
Termination Cap Specification Chart
(Depth without using additional pipe sections)
SLP-TRAP1 can adjust 2-3/8 in. (4-1/8 in. to 6-1/2 in.)
SLP-TRAP2 can adjust 4-1/2 in. (6-1/2 in. to 11 in)