Chapter 5, Installation and Configuration
5-13
22.Press the YES key to abort the procedure and verify the Abort
Procedure Confirmation screen is displayed.
23.Press the DRAW key to abort the procedure and verify the Procedure
Statistics screen is display.
24.Remove the test disposable set and verify the machine advances to the
Systems Test screen.
Leakage Current
1. Plug the PCS2 into the Leakage Tester (Dale Technologies LT544D
Lite or equivalent).
2. Plug the Leakage Tester into a grounded electrical outlet.
3. Set the meter switch settings as follows:
• Leakage
• Neutral Closed
• Polarity Normal
4. Turn on the PCS2.
5. Note the reading in microamperes on the meter.
6. Depress the GND switch on the meter.
7. Change the Polarity switch from Normal to Reverse.
8. Verify the readings do not exceed 100 microamperes at 120 VAC and
500 microamperes at 240 VAC.
Ground Continuity
1. Change the meter mode to RESISTANCE.
2. Plug the ground wire (coiled wire with clip) into the grounding socket
on the Leakage Meter.
3. Attach the clip to the following exposed metal locations. Verify that
there is continuity.
• Pump - rotor screws
• Rear Panel hardware
• Front panel hardware
• Pinch valve plungers
4. Verify the highest reading is less than 1 Ohm.