Commissioning
42 | 76
6.1.2
Manual start of the commissioning program
If required, start the start-up program manually from the menu level.
Status level>Menu level>Start-up
1.
Confirm with ENTER.
2.
Press and hold the ▲ and ▼ keys for 2 seconds.
6.1.3
Sequence of the start-up program
There can be waiting periods during the start-up program. These are indicated in
the control unit by means of an hourglass symbol. Continuing with the program is
only possible upon completion of the waiting period and the disappearance of the
symbol.
Use the ▲ or ▼ keys to navigate through the program.
1.
Do not fill any water in the brine tank.
2.
Confirm with ▼.
3.
Fill salt tablets into the brine tank (refer to chapter 7.8).
4.
Confirm with ▼.
5.
Set the current time and the current date.
a
Set the desired value using▲ and ▼.
b
Confirm with ENTER.
The system moves to its reference point. In case the reference point has not
been reached until after the entry of the time, the remaining time will be
indicated in the display.
6.
Determine the raw water hardness. You have the following options to do so:
• Contact your water supply company and ask them what the value is.
• Determine the value by using the water test kit supplied with the system (refer
to chapter 7.7).
7.
Use ▲ and ▼ to set the value ascertained for the raw water hardness.
8.
Confirm with ENTER.
Confirmation is only possible if the system has completed the previous step.
This is the case when the ENTER button lights up. The value can be
changed subsequently (refer to chapter 7.7).