INSTALLATION
66
Purge and make leakage
detection under pressure
◆
Purge the system clean.
◆
Keep the pressure for 24 hours
◆
Except for the influence by temperature, it is deemed
acceptable if pressure drop is within 0.02MPa. (With the
temperature change by 1 , the pressur
℃
e will change by
approx. 0.01MPa)
Thermal insulation
◆
The thermal insulation tube must meet the specifications.
◆
Seal between the thermal insulation pipes to avoid air
entry.
Installation of outdoor unit
◆
Select the installing position correctly.
◆
Build the foundation according to the anchor bolt position
and the dimension of outdoor unit
◆
Build the damping device properly.
◆
Avoid sharp knock when handling the outdoor unit. The
inclination angle shall not be higher than 15°.
Connection of indoor unit and outdoor unit
◆
Tighten the nuts.
◆
Provide proper protection to the outdoor connection pipe,
communication wires and power supply.
Leakage detection under pressure
◆
Keep the pressure for 24 hours. Except for the influence by
temperature, it is deemed acceptable if pressure drop is
within 0.02MPa. (With the temperature change by 1
℃
, the
pressure will change by approx. 0.01MPa).
Vacuuming
◆
Establish vacuum simultaneously in the gas pipe and liquid
pipe;
◆
The vacuuming time shall be long enough.
◆
Put still for 1 hour after vacuuming. It is deemed
acceptable if the pressure will not rise.
Add refrigerant
◆
Add refrigerant according to the volume as specified on the
engineering drawing.
Open the valve of outdoor unit
Commissioning of complete unit
Remarks:
a. Described above are general working procedures. The procedures might vary with the site conditions.
b. For detailed installation rules, please see the description in each chapter
Summary of Contents for R410A
Page 1: ...SUPER FREE MATCH SERIES SERVICE MANUAL T1 R410A 50Hz GC201306 CENTRAL AIR CONDITIONERS ...
Page 5: ...Super Free Match Service Manual PRODUCT 1 PRODUCT ...
Page 28: ...Super Free Match Service Manual CONTROL 24 CONTROL ...
Page 29: ...Super Free Match Service Manual CONTROL 25 Control 1 OPERATION FLOWCHART ...
Page 31: ...Super Free Match Service Manual CONTROL 27 1 2 Heating Operation ...
Page 66: ...Super Free Match Service Manual INSTALLATION 62 INSTALLATION ...
Page 97: ...Super Free Match Service Manual INSTALLATION 93 ...
Page 129: ...Super Free Match Service Manual MAINTENANCE N 125 MAINTENANCE ...
Page 153: ...Super Free Match Service Manual MAINTENANCE N 149 4 2 3 BU module FXB3A K ...
Page 154: ...Super Free Match Service Manual MAINTENANCE 150 FXB5A K ...
Page 217: ...JF00301896 ...