Service Manual
INSTALLATION
110
Pipe diameter
Thickness of
copper tube
Tightening torque
Φ
6.35 mm
≥
0.8 mm
15
~
30 N·m
Φ
9.52 mm
≥
0.8 mm
35
~
40 N·m
Φ
12.7 mm
≥
0.8 mm
45
~
50 N·m
Φ
15.9 mm
≥
1.0 mm
60
~
65 N·m
Φ
19.05 mm
≥
1.0 mm
70
~
75 N·m
During the connection of the indoor unit and BU module to the refrigerant pipe, never pull any joints of the
indoor unit and the BU module by force; otherwise the capillary pipe or other pipe may crack, which then
would result in leakage.
The refrigerant pipe should be supported by brackets, that is, don’t let the unit withstand the weight of it.
For the Super Free Match system, each pipe should be labeled to tell which system it belongs to avoid
mistaken inaccurate piping.
6.9
Leak Test
1)
Please make sure that the stop valves of the outdoor unit are closed during the operation.
2)
The leak test should be made by pressurizing nitrogen gas.
3)
Open the pressure reducing valve, pressurize the connection pipes to 1.0 MPa (10 bar) slowly, wait ten
minutes, and make sure that the pressure will not drop.
4)
Rise the pressure to 4.0 MPa (40 bar) slowly, wait 24 hours, and make sure the pressure will not drop.
5)
If the pressure does not decrease, the pipes have passed the test. Otherwise, look for where the gas leaks
from.
1: Outdoor unit
2: Liquid side stop valve
3: Gas side stop valve
4: Pressure-vacuum gauge
5: Hi-knob
6: Lo-knob
7: Pressure reducing valve
8: Nitrogen
6.10
Vacuum Operation
1)
Make sure that the liquid and gas stop valve of the outdoor unit are closed fully during the operation.
2)
As shown in the following figure, expel the gas from the refrigerant pipes by the vacuum pump.
1: Outdoor unit
2: Liquid side stop valve
3: Gas side stop valve
4: Pressure-vacuum gauge
5: Hi-knob
6: Lo-knob
7: Vacuum pump
Summary of Contents for R410A
Page 1: ...SUPER FREE MATCH SERIES SERVICE MANUAL T1 R410A 50Hz GC201306 CENTRAL AIR CONDITIONERS ...
Page 5: ...Super Free Match Service Manual PRODUCT 1 PRODUCT ...
Page 28: ...Super Free Match Service Manual CONTROL 24 CONTROL ...
Page 29: ...Super Free Match Service Manual CONTROL 25 Control 1 OPERATION FLOWCHART ...
Page 31: ...Super Free Match Service Manual CONTROL 27 1 2 Heating Operation ...
Page 66: ...Super Free Match Service Manual INSTALLATION 62 INSTALLATION ...
Page 97: ...Super Free Match Service Manual INSTALLATION 93 ...
Page 129: ...Super Free Match Service Manual MAINTENANCE N 125 MAINTENANCE ...
Page 153: ...Super Free Match Service Manual MAINTENANCE N 149 4 2 3 BU module FXB3A K ...
Page 154: ...Super Free Match Service Manual MAINTENANCE 150 FXB5A K ...
Page 217: ...JF00301896 ...