Key Points of Installation
Installation Procedures
Description and Acceptance Criteria
Material Selection and Equipment Inspection
◆
The materials specified on the engineering drawing shall
be purchased as specified (e.g. copper tube, thermal
insulation tube, PVC pipe, power cables, air switch, etc).
◆
The materials not specified on the engineering drawing
shall be purchased according to the actual quantity of
works (e.g. hanger frame, cable duct, etc).
◆
Check if the outdoor unit, indoor unit, BU modules,
communication wires and accessories are complete.
Connection
◆
The power cables shall be separated from communication
wires at a least distance of 2cm.
◆
To avoid breaking the communication wires, please do not
use strong force.
◆
For multiple units, please mark them properly.
◆
Switch on the unit, and ensure there is no display of
“Communication Wire Error E6”.
Communic
ation wire
Address dial
code
◆
Each BU module and indoor unit under the same system
has a unique address dial code.
◆
The wired controller and its corresponding indoor unit
have the same address dial code.
Remote Control
◆
Select the remote control mode.
◆
The centralized controller and communication module
shall be installed free from the source of interference.
Power cord
◆
The power cable must meet the specifications.
Installation
◆
The PVC pipes must meet the specifications.
◆
A specific gradient must be provided along the water flow
direction.
◆
Carry out water detection after installation.
◆
Carry out thermal insulation to the drainage pipe only after
the water detection is accepted.
Installation of
indoor unit
Drainage
Pipe
Thermal
insulation
◆
The thermal insulation tube must meet the specifications.
◆
Seal between the thermal insulation pipes to avoid air
entry.
Installation of
connection
pipes
Welding
◆
The copper tube must meet the specifications.
◆
Ensure it is dry and clean inside the tube.
◆
Make sure to charge nitrogen as required for protection
when welding the tubes.
◆
Please keep to the welding process and ensure the system
free of leakage.
◆
Add a dual-way filter on liquid pipe side
◆
For multiple systems, please mark them properly.
◆
Carry out leakage detection under pressure after welding.
Summary of Contents for R410A
Page 1: ...SUPER FREE MATCH SERIES SERVICE MANUAL T1 R410A 50Hz GC201306 CENTRAL AIR CONDITIONERS ...
Page 5: ...Super Free Match Service Manual PRODUCT 1 PRODUCT ...
Page 28: ...Super Free Match Service Manual CONTROL 24 CONTROL ...
Page 29: ...Super Free Match Service Manual CONTROL 25 Control 1 OPERATION FLOWCHART ...
Page 31: ...Super Free Match Service Manual CONTROL 27 1 2 Heating Operation ...
Page 66: ...Super Free Match Service Manual INSTALLATION 62 INSTALLATION ...
Page 97: ...Super Free Match Service Manual INSTALLATION 93 ...
Page 129: ...Super Free Match Service Manual MAINTENANCE N 125 MAINTENANCE ...
Page 153: ...Super Free Match Service Manual MAINTENANCE N 149 4 2 3 BU module FXB3A K ...
Page 154: ...Super Free Match Service Manual MAINTENANCE 150 FXB5A K ...
Page 217: ...JF00301896 ...