Test Operation, Troubleshooting and Maintenance
Replacement of the electric expansion valve
Note: check the whole system, pipelines and electric lines, cut off power supply and reclaim
refrigerant before replacement.
Steps
Image
Instructions
5. Replace it with
a new one.
•
Solder pipes.
•
Do charge nitrogen during soldering;
•
Protection measures should be
taken during soldering to prevent
surrounding objects from being burnt
out.
6. Tighten coils,
pipe clamps and
rubber pads;
vacuum the
system; recharge
refrigerant and
then put back the
panel.
•
The bulge of the coil should match
with the re cess of the main body of
the valve.
•
Keep the vacuum degree to -1.0bar.
Vacuuming period would be longer
for the repaired unit.
•
Charged refrigerant should be
the same as that stated at the
nameplate.
• Power off the unit and then power it
on again.
•
Put back the panel.
Replacement of the vapor-liquid separator
Note: properly reclaim refrigerant, prepare tools and keep good ventilation.
Steps
Image
Instructions
1. Remove front
panels.
• Remove screws at the front panel.
• Loosened screws should be put
together to avoid loss.
• Pull the front panel upwards and
then remove it.
•
Properly keep the removed front
panel to avoid from being damaged.
• Note that there are two clasps at
each panel for connecting with side
panels.
Summary of Contents for LSQWRF35VM/NaA-M
Page 5: ...1 Product Product...
Page 18: ...14 Unit Control Unit Control...
Page 29: ...25 Unit Installation Unit Installation...
Page 58: ...54 Unit Installation 3 5 7 Electric wiring digram 1 LSQWRF35VM NaA M...
Page 59: ...55 Unit Installation 2 LSQWRF60VM NaA M LSQWRF65VM NaA M...
Page 60: ...56 Unit Installation 3 LSQWRF35VM NhA M...
Page 61: ...57 Unit Installation 4 LSQWRF60VM NhA M...
Page 62: ...58 Unit Installation 5 LSQWRF130VM NhA M...
Page 63: ...59 Unit Installation...
Page 64: ...60 Unit Installation The electric wiring diagrams on the unit always prevail...