4 Test operation, troubleshooting and maintenance
4.1 Commissioning
4.1.1 Flowchart of commissioning
Preparation
Check on installation
Check on the unit
Commissioning
4.1.2 Safety precautions for commissioning
WARNING
•
Safety measures should be taken during indoor operation. Any commissioning and service personnel
should grasp and observe safety regulations of construction work.
• Refrigeration mechanic, electricians, welders and other technicians of other special work all should be
licensed.
• Power supply should be cut off before any operation to the unit. Meanwhile, please observe required
safety operation.
• All installation and operation should comply with design requirements of this product and local safety
requirements.
•
Never force the compressor to run by electrifying it directly.
4.1.3 Preparation before commissioning
(1) Manual of installation instructions
(2)
Certificate of qualification
(3)
Electric wiring diagrams
(4) Sheet of saturated temperature and pressure
4.1.4 Check before commissioning
◆
Check the completeness
(1) Is the surface of the unit in good condition?
(2) Is there leak at any pipe connector?
(3) Is any part damaged?
◆
Check installation of the unit
Do the installation location, installation foundation and maintenance space comply with corresponding
requirements?
◆
Check the water system
Summary of Contents for LSQWRF35VM/NaA-M
Page 5: ...1 Product Product...
Page 18: ...14 Unit Control Unit Control...
Page 29: ...25 Unit Installation Unit Installation...
Page 58: ...54 Unit Installation 3 5 7 Electric wiring digram 1 LSQWRF35VM NaA M...
Page 59: ...55 Unit Installation 2 LSQWRF60VM NaA M LSQWRF65VM NaA M...
Page 60: ...56 Unit Installation 3 LSQWRF35VM NhA M...
Page 61: ...57 Unit Installation 4 LSQWRF60VM NhA M...
Page 62: ...58 Unit Installation 5 LSQWRF130VM NhA M...
Page 63: ...59 Unit Installation...
Page 64: ...60 Unit Installation The electric wiring diagrams on the unit always prevail...