Chapter 4 - System Covers: Installation & Alignment
Page 167
- Con
tinui
ty Checks
Section 7.0 Mechanical Installation Completion Checklist
System-Level
FE Service cabinet moved to the location shown on the site print
All covers installed and aligned
All options installed on the table and gantry
All packing materials and boxes returned to the lean cart
All service items placed in the service cabinet.
Optional and Regional
Seismic mounting installed, if required in your area.
Site Clean Up
All customer items placed on a cabinet or on a counter and labeled customer material.
All system service tools placed in the GE service cabinet.
System software and options left on the lean cart in the software tray
System cleaned and nicks repaired
Installation site cleaned and all trash properly disposed.
Dolly Return
Return of dollies and lean carts arranged for and pick-up made.
Paperwork
Mechanical installation section of the GE Form e4879 completed
Room information recorded on the GE Form e4879
Table gantry alignment completed per the installation manual
Table gantry anchoring completed per the installation manual
GE Healthcare personnel notified that the mechanical installation is completed
All installation issues have been addressed and or documented so FE can follow-up as needed.