Procedure
A.
Vertical Delivery Pipes Assembly
•
Using a spirit level, find the highest point on the forecourt out to a distance of 160mm
from the main column (in any direction). Transfer this point onto the front face of the
column (front = sump at right hand side of column) and mark it as a datum point on
the face of the column. It must be established as an initial point to start measuring the
positions of components and mounting brackets and to obtain mounting heights and
ground clearances for final cladding.
Figure 8.
Vertical Delivery Pipes Assembly Mounting Positions
2A03229 APOLLO 3000L Installation and Commissioning Manual Issue 1
12
APOLLO 3000L INSTALLATION