Safety Inspection
(power-off)
Switch power on
Fail
Standalone
Forecourt
Controller or
Standalone?
Set pump numbers
Check 5/6 digit setting
Set date and time
Upgrade firmware if necessary
Ensure POS provider system is set to
MPD and correct protocol is used
Perform Hydraulic
Stack Test
Calibrate
Set grade prices
Return to Install Procedure
ENTER SERVICE
START COMMISSIONING
Set date and time
Upgrade firmware if necessary
3
APOLLO 3000L COMMISSIONING
The following chart gives an overview of the commissioning process.
3.1 Safety Inspection
Before the fuel and electrical supply are turned on for the first time the installation
must be inspected and approved for safety by suitably qualified personnel.
Items that must be checked during safety test include:
• VR2 return line connections (where present);
• Electrical power supply connections;
• Remote relay connections;
• Communications cabling and connections;
• Fuel feed line connections.
3.2 Dispenser Configuration and Setup
The dispenser is supplied with an specific configuration loaded onto the SD card on
the Central Controller Module. However, following the physical installation of the
dispenser, the system must be configured via the Service Mode prior to use.