![Foundry Networks NetIron MLX-16 Installation And Configuration Manual Download Page 65](http://html1.mh-extra.com/html/foundry-networks/netiron-mlx-16/netiron-mlx-16_installation-and-configuration-manual_2324265065.webp)
Installing a NetIron MLX Series Router
December 2008
© 2008 Foundry Networks, Inc.
3-25
Figure 3.19 Installing a Module in a NetIron MLX-16 Chassis
NOTE:
The installation instructions for installing modules shown in the following illustrations are exactly the
same for interface, management, and switch fabric modules.
5.
Tighten the two screws at either end of the module front panel by pushing them in and turning them
clockwise. Then, tighten the screws further using the flat-head screwdriver.
Populating a NetIron MLX-16 Chassis
The sequence for installing more than one card is important to ensure proper fit in the NetIron MLX-16 chassis.
Always fill the bottom slots in the NetIron MLX-16 first. Begin by filling the slots from the left side of the chassis,
and working your way towards the right. See “ NetIron MLX-16 Chassis” on page 2-4 for slot locations.
NOTE:
Any empty slots must contain slot blanks to ensure proper air flow within the chassis.
Rules for Populating a NetIron MLX-16 Chassis
1.
Install a management module in management slot 2.
2.
Install interface modules in interface slots 2, 4, 6, and 8.
3.
Install switch fabric modules in the switch fabric slots 2 and 4.
4.
Install interface modules in interface slots 10, 12, 14, and 16.
5.
Install a management module in management slot 1.
6.
Install interface modules in interface slots 1, 3, 5, and 7.
7.
Install switch fabric modules in the switch fabric slots 1 and 3.
8.
Install interface modules in interface slots 9,11,13, and 15.
Installing Power Supplies in a NetIron MLX-16 Chassis
To install a power supply in a NetIron MLX-16 chassis, do the following:
1.
Remove the blank power supply faceplate, and expose the empty power supply slot.
Interface Module