1.16.
Lifting Cube 80/100
All Cube units are equipped with handles for ropes, localized in upper part, allowing to lift the unit. Spreader beam application is
not necessary. Handles for lifting the unit and heat module are indicated in pictures below.
•
Because of load distribution, minimum length of hoisting ropes from handle to hook is 3,5 m. Disobeying this
recommendation may result in damage to unit or even mounting breach.
•
The Cube 80/100 L cannot be raised with the heat recovery module attached. Installation of the heat recovery module
to the Cube 80/100 L device should be done on the roof, after mounting the Cube device. Installation is carried out in
accordance with the guidelines presented later in this manual.