4
Commissioning
Festo – P.BE-CPX-CTEL-EN – 1601b – English
29
4.3
Preparing the CTEL system for commissioning
Note
Addressing errors caused by changing address ranges during operation
Do not connect the CPX terminal to a higher-order controller yet to prepare for com
missioning.
The integration of the CTEL master module into the host system might have to take place
via a device description file, dependent on the CPX bus node used. Corresponding device
description files can be found in the Festo Support Portal (
è
www.festo.com/sp).
Check the CTEL master module and the connected I-Port devices
Check the position of the DIL switches to guarantee the desired configuration presetting
(
è
Check the CTEL master module to ensure it is securely seated in the interlinking block.
Check whether the connected I-Port devices correspond to the entry of the configuration file in
the host system (
è
3.6 Connection with the host system).
Check whether the connected I-Port devices are distributed to the I-Ports corresponding to their
priority for diagnostic/error messages (
è
5.2.1 Priorities of the diagnostic/error messages).
Check whether the current consumption of the connected I-Port devices and the other CPX modules
corresponds to the specifications and limit values (
è
3.5 Connecting the power supply).
Check the power supply connections at the interlinking blocks.