12. MAINTENANCE
RISKS
PERSONAL PROTECTIVE EQUIPMENT
F
Always shut off the power supply before performing
any maintenance operations. If the disconnect
switch is not in view, apply a warning sign stating
“WARNING - Maintenance in Progress”. Restore the
power supply only after finishing any maintenance
work and restoring the area to normal.
Do not remove the board cover. No maintenance
requires the removal of the cover.
!
The barrier must not be left released. If the barrier
is put out of order for a long time, the beam needs
to be removed.
Maintenance must be performed by the installer or a
maintenance technician.
Follow all safety recommendations and instructions
given in this manual.
Mark off the work site and prohibit access/transit. Do
not leave the work site unattended.
The work area must be kept tidy and cleared after
maintenance has been completed.
Before starting work, wait for any hot components
to cool down.
Do not make any modifications to the original
components.
FAAC S.p.A. shall bear no liability for damage or
injury due to components that have been modified
or otherwise tampered with.
L
i
The warranty shall be forfeited in the event of tam-
pering with components.
Only use original FAAC spare parts.
12.1 ROUTINE MAINTENANCE
The
Scheduled maintenance
lists, purely for guidance
which is not intended to be exhaustive, the operations
which must be performed on a regular basis to keep
the automation system safe and in good working
order. The installer/machine manufacturer is re-
sponsible for drawing up the maintenance plan for
the automation, supplementing this list or modifying
the maintenance intervals according to the machine
characteristics.
1 3
Routine maintenance
If the tests listed below turn up conditions that are
other than expected, repair or restoration is neces-
sary. The plant must not be put back into operation
until all the safety precautions specified in this manual
and in the documentation of all the other components
installed have been complied with.
Operations Frequency/months
Structures
Check the plinth and built/fenced parts around the automa-
tion system: make sure there is no damage, cracking, breaks
or subsidence.
12
Check the area the beam moves in: make sure there are no
objects/deposits that reduce the uncluttered safety areas and
obstacles to the movement of the beam such as branches,
overhead wires etc.
12
Ensure that there are no sharp protrusions which could
represent a perforation or hooking hazard.
12
Barrier
Check the fixing of the bearing box to the foundation plate. 6
Check the barrier and its fixings: integrity, absence of defor-
mation, rust etc.
Check that screws and bolts are correctly tightened.
12
Check the condition of the beam and that it is fastened
properly.
12
Check the condition of the beam and that it is fastened
properly.
12
Check the presence and integrity of the reflectors on the beam
and all the other signs and markings necessary.
6
Check the integrity and proper fixing of the spring and tie
rods.
12
Check the configuration and the balancing of the barrier.
12
Check the integrity, proper functioning and adjustment of
the limit switch.
12
Check the integrity of all the cables, cable glands and
junction boxes.
12
Check that it is irreversible.
12