Card Descriptions
Table 85
Facility LEDs on Controller Cards
Label
Activity
Color
Description
On
Green
The link is present and active.
Blinking
Green
The link is transmitting or receiving frames.
LINK/ACTIVITY
LINK/ACT
Off
None
The link has no active frame.
On
Green
The link is operating at 1 Gbps (XCRP4 only)
On
Yellow
The link is operating at 100 Mbps.
SPEED
Off
None
The link is operating at 10 Mbps.
Table 86
Synchronization and External Timing LEDs on Controller Cards
Label
Activity
Color
Description
On
Green
At least one of the selected synchronization references is in good
condition and is providing reference.
SYNC
Off
None
The selected synchronization reference is external, and all external
references have failed. The timing is being internally generated.
On
Yellow
The primary input signal from the external equipment has been
configured (provisioned), but is not present.
EXTERNAL TIMING
LOS PRI
Off
None
The primary input signal has not yet been configured or has been
configured and is present.
On
Yellow
The secondary input signal from the external equipment has been
configured but is not present.
EXTERNAL TIMING
LOS SEC
Off
None
The secondary input signal has not yet been configured or has been
configured and is present.
6.1.2
Supporting Information
The following sections provide information about functional components of
the XCRP4 Controller card.
6.1.2.1
Processors
The XCRP4 Controller card has four processors: one processor runs the
low-level software and the other three processors run the BRAS and routing
software. Support for more than one processor to run the BRAS and routing
software depends on the release of the SmartEdge OS.
6.1.2.2
Main Memory
Synchronous Dynamic Random Access Memory (SDRAM) is used by the
SmartEdge OS shared databases that are accessed by the line cards. In a
chassis with two controller cards, both cards must have the same memory
configuration
111
27/153 30-CRA 119 1170/1 Uen A
|
2010-04-09
Summary of Contents for SmartEdge 600
Page 1: ...SmartEdge 600 Router Hardware Guide Release 6 3 INSTALLATION 27 153 30 CRA 119 1170 1 Uen A ...
Page 6: ...SmartEdge 600 Router Hardware Guide 27 153 30 CRA 119 1170 1 Uen A 2010 04 09 ...
Page 26: ...SmartEdge 600 Router Hardware Guide 20 27 153 30 CRA 119 1170 1 Uen A 2010 04 09 ...
Page 108: ...SmartEdge 600 Router Hardware Guide 102 27 153 30 CRA 119 1170 1 Uen A 2010 04 09 ...
Page 112: ...SmartEdge 600 Router Hardware Guide 106 27 153 30 CRA 119 1170 1 Uen A 2010 04 09 ...