22
E D G E I Q H A N D B O O K
The screw holding the cable of line and neutral
has been correctly torque. (torque setting:
20.4Kgf.cm minimum
)
Note: Both the input and output of the EdgeIQ must
have an earth connected (at the same potential)
A.6
M2M modem should be connected to the correct
port as shown on sticker in unit
Please tick when this step is completed:
Yes
Note: Port for the M2M modem (dongle) is the back
left, closest to the middle of the unit
A.7
External comms antenna connected has been
connected properly to M2M modem
Please tick when this step is completed:
Yes
Ensure locking nut of the antenna cable and the
rubber seal washer are correctly installed
A.8
Confirm that the CT is clamped to the line wire of
the solar inverter line cable?
Please tick when this step is completed:
Yes
Ensure the CT direction is correct and cable
insulation is undamaged. (Arrow is in the direction of
current flow)
B
Electrical testing
Summary of Contents for EDGEIQ EE-202-0050
Page 1: ...1 2 3 INSTALL THE WORLD S BEST VOLTAGE OPTIMISATION TECHNOLOGY ...
Page 2: ......