UPS Installation Plan and Unpacking
3-28
Power Xpert
TM
9395 UPS (450–825 kVA) Installation and Operation Manual
164201725—Rev 10
www.eaton.com/powerquality
2.
Use a forklift or pallet jack to move the packaged cabinet to the installation site, or as close as possible,
before unpacking. If possible, move the cabinet using the pallet. Insert the forklift or pallet jack forks from
the right side of the pallet (facing the cabinet), between the supports on the bottom of the pallet (see
Figure 3-13 for the UPS cabinet center of gravity measurements). If the cabinet must be moved using the
cabinet front or rear fork lift slots, see the caution statement at the beginning of this procedure.
CAUTION
Do not tilt the UPS cabinet more than 10º from vertical or the cabinet may tip over.
3.
Set the pallet on a firm, level surface, allowing a minimum clearance of 3m (10 ft) on each side for
removing the cabinet from the pallet.
4.
Remove the protective covering from the cabinet.
5.
Remove the packing material, and discard or recycle in a responsible manner.
6.
Inspect the contents for any evidence of physical damage, and compare each item with the Bill of Lading.
If damage has occurred or shortages are evident, contact an Eaton service representative immediately to
determine the extent of the damage and its impact on further installation.
NOTE
The ISBM and UPM sections are shipped with debris shields covering the
ventilation grills on top of the sections (see Figure 3-14). Do not remove the debris
shields until installation is complete.
NOTE
While waiting for installation, protect the unpacked cabinet from moisture, dust, and
other harmful contaminants. Failure to store and protect the UPS properly may void
your warranty.
Summary of Contents for Power Xpert 9395 UPS
Page 2: ......
Page 27: ...Installation ...
Page 28: ......
Page 123: ...Section 2 Operation ...
Page 124: ......
Page 249: ......
Page 250: ... 164201725 10 164201725 10 ...