Table 3-5. Input/Output Ratings and External Wiring Requirements for the Three UPM Power Xpert 9395-825/650, 9395-825/750, and 9395-825/
825 – Separate Battery
Basic Unit Rating
Units
Rating 50/60 Hz
kVA
kW
650
592
650
592
750
683
750
683
825
751
825
751
Input and Output Voltage
Volts
400/400
480/480
400/400
480/480
400/400
480/480
AC Input to UPS Rectifier (0.98 Minimum pF)
Full load current plus battery recharge current
(3) Phases, (1) Ground
A
Amps
1070 892 1234 1029
1358
1132
Minimum Conductor Size
Number per Phase
AWG or kcmil
(each)
500
(4)
500
(3)
500
(4)
500
(4)
500
(5)
500
(4)
AC Input to UPS Bypass (Four Wire)
Full Load Current
(3) Phases, (1) Ground
B
Amps
938 782 1083 902
1191
992
Minimum Conductor Size
Number per Phase
AWG or kcmil
(each)
500
(3)
350
(3)
500
(4)
500
(3)
500
(4)
500
(4)
AC Input to UPS Bypass (Five Wire)
Full Load Current
(3) Phases, (1) Neutral, (1) Ground
B
Amps
938 782 1083 902
1191
992
Minimum Conductor Size
Number per Phase
AWG or kcmil
(each)
400
(4)
500
(3)
500
(5)
500
(4)
500
(5)
500
(5)
DC Input from Each Battery Disconnect to Each
UPS UPM
(1) Positive, (1) Negative
C
Amps per UPM
551
551
551
551
551
551
Minimum Conductor Size
Number per Pole
AWG or kcmil
(each)
250
(3)
250
(3)
250
(3)
250
(3)
250
(3)
250
(3)
AC Output to Critical Load (Four Wire)
Full Load Current
(3) Phases, (1) Ground
D
Amps
938 782 1083 902
1191
992
Minimum Conductor Size
Number per Pole
AWG or kcmil
(each)
500
(3)
350
(3)
500
(4)
500
(3)
500
(4)
500
(4)
AC Output to Critical Load (Five Wire)
Full Load Current
(3) Phases, (1) Neutral, (1) Ground
D
Amps
938 782 1083 902
1191
992
Minimum Conductor Size
Number per Pole
AWG or kcmil
(each)
400
(4)
350
(3)
500
(5)
500
(3)
500
(5)
500
(4)
NOTE
V
Callout letters
A
,
B
,
C
, and
D
map to Figure 6-6, Figure 6-8 or Figure 6-12. Callout letters
A
,
C
, and
D
map to Figure 6-14 or Figure 6-16. Callout letters
B
,
C
, and
D
map to Figure 6-20. Callout letters
C
, and
D
map to Figure 6-21 or Figure 6-22.
NOTE
V
Bypass wiring data is not applicable to IOM configurations
.
Battery Conductor Sizing
: Eaton strongly recommends using the specified DC conductor size and quantity shown above for optimum system performance and
battery run time.
Battery Cable Routing Requirements
Conduit applications:
* Each conduit must have a Positive, Negative, and Ground conductor.
* There must be an equal number of positive and negative conductors in a single conduit. Only one ground conductor is required in each conduit.
Raceway applications:
* Positive and negative battery cables must be run side by side in the raceway in an alternating pattern (+ - + - + - + -).
* There must be a ground cable running in the raceway with the battery cables.
Summary of Contents for Power Xpert 9395 UPS
Page 2: ......
Page 27: ...Installation ...
Page 28: ......
Page 123: ...Section 2 Operation ...
Page 124: ......
Page 249: ......
Page 250: ... 164201725 10 164201725 10 ...