EFX48-xx Series with RM3-340/440 Installation and Operation Guide
70
Copyright © 2019 Eaton Corporation. All Rights Reserved.
IPN March 2019
Start-Up Tasks
Complete all the Installation tasks (see details on page 55) before starting these Start-Up tasks.
Complete the Start-Up tasks in the following order:
Task Description
Reference
1
Insert the rectifiers
See details on page 70
2
Complete the Pre-Power-Up Checklist
See details on page 71
3
Connect to the ac supply
See details on page 71
4
Configure the dc power system
See details on page 72
5
Apply dc power to battery and load
See details on page 73
Task 1 - Inserting the Rectifiers
•
Do NOT install the rectifiers until the room has been cleaned and is dust free.
•
Do NOT switch on the ac supply at this stage.
Step 1 - Unpack the rectifiers
Unpack the rectifiers and inspect them carefully for possible transport damage.
Report any damage immediately using a completed Equipment Incident Report on
page 159.
Keep the original packaging to return a rectifier for replacement or repair, if
required.
Step 2 - Fit first rectifier
1
Align the rectifier with the left side of the shelf.
2
Push in the rectifier until the retaining screw contacts the shelf.
3
Check the rectifier's rear connector is correctly aligned with the shelf connector,
or damage may occur.
4
Tighten the retaining screw to 1.5Nm (13.3 inch-pounds). This will locate the
rectifier in its rear connector.
Summary of Contents for EFX48 e-Fuse Series
Page 9: ......
Page 50: ......
Page 54: ......
Page 88: ......
Page 157: ...Menu Map Copyright 2019 Eaton Corporation All Rights Reserved IPN March 2019 157...