When the time for a
Battery Test
has been reached the following qualification conditions need
to be met before a test is allowed to start :
Battery Test Qualification Conditions
Must be true
System AC fail alarm condition not active
Battery test is enabled
The system must have been in the float state for
the qualification time
There must be no pending or tripped strings
Equalisation is not being performed
Fast charge is not being performed
There is not a manual battery test already in
progress
Rect fail alarm or Multi rect alarm conditions not
active
Rectifier Comms alarm condition not active
System Overcurrent alarm condition not active
System Overload alarm condition not active
Summary of Contents for EFX48 e-Fuse Series
Page 9: ......
Page 50: ......
Page 54: ......
Page 88: ......
Page 157: ...Menu Map Copyright 2019 Eaton Corporation All Rights Reserved IPN March 2019 157...