OPERATORS MANUAL
14
May 1997 – 5B6729
Figure 5
Installing the Evaporation Covers
[4] Check that developer and fixer solutions are near the overflow levels of each Tank.
[5] Install the Evaporation Covers on the Crossovers and the Top Cover on the Processor.
[6] Turn on the water supply.
Important
The incoming water temperature should be between 4 and 29
°
C (40 and 85
°
F).
[7] Remove any film from the Feed Tray.
[8] Move the wall power switch to the “ON” position.
[9] Move the main Circuit Breaker CB1 to the “ON” position.
[10] For optimum processing quality, allow approximately 20 minutes for the processing solutions to reach the
correct operating temperature before you feed film. The Ready Indicator will illuminate once the solutions have
reached the correct temperature.
Performing the Shutdown Procedure
Note
You can also program the Processor to shut down automatically by setting the Automatic Off Timer. See Page
for the procedure on how to set the Automatic Timers.
[1] Move the main Circuit Breaker CB1 to the “OFF” position.
[2] Move the wall power switch to the “OFF” position.
[3] Turn off the water supply.
H148_0036BA
H148_0036BCB
Evaporation Covers