4–36
INSTALLATION
If an electrician constructs the power distribution cables, it is
HIGHLY
RECOMMENDED that these cables be of similar construction as those described in
the previous paragraph to maintain Digital’s "Single Point Grounding Strategy" for
maximum computer system reliability.
4.6.5 Checks After Installation
After installing the UPS Distribution Cabinet, make the following checks:
1. Check that all power and control wires have been properly connected and securely
tightened.
2. Verify that the input voltage to the HA32J/K UPS Distribution Cabinet is that shown
on the UPS Distribution Cabinet nameplate located inside the right door of the UPS
Distribution Cabinet.
3. Reinstall the distribution panel cover and the conduit cover panel.
Summary of Contents for HA3000