INSTALLATION REFERENCE CHECKLISTS
1–9
1.4 DIGITAL SERVICES RESPONSIBILITIES
The following sections contain the responsibilities of Digital Services during site
preparation, delivery/handling, and initial startup of the HA3000 series UPS.
1.4.1 Site Preparation
Digital Services responsibilities during site preparation are listed below.
Check Off
Function
Task
Physical Size and
Weight
Aid the customer in obtaining the size and weight
information on the HA3000 series cabinets that
are to be installed. Refer to the
HA3000 20-80 kVA
Uninterruptible Power System Installation Drawings
(EK-HA32X-ID) or to Chapter 2 in this manual.
Electrical
Requirements
Aid the customer in ensuring that the customer’s
electrician has the documentation and electrical
requirements necessary for performing the installation.
Physical Placement
Aid the customer in determining the exact physical
placement of the cabinets. The cabinet dimensions and
service clearances must be taken into consideration.
The following is a list of the
minimum service
clearances required.
Rear - 60.96 cm (24 in)
Front - 121.92 cm (48 in)
Side - 60.96 cm (24 in) on each end of the cabinet
configuration
Top - 91.44 cm (36 in)
NOTE: Local codes may require more clearance.
Configuration Layout
Aid the customer in planning the configuration layout
using the following placement order (left to right):
UPS Battery Cabinet(s), UPS cabinet, UPS Auxiliary
Cabinet, UPS CSA Cabinet, and UPS Distribution
Cabinet.
Inside Delivery
Route
Aid the customer in ensuring that there is an
unobstructed inside delivery path to the final
installation position. Aid the customer in ensuring
that elevators, ramps, and flooring along this path can
handle the equipment weights and dimensions.