Two-Post Rack Installation
33
Figure 2-4.
Installing the Mounting Rails for Center-Mount Configuration
Flush-Mount Installation
The two-post rack kit is shipped with the brackets configured for a 7.62-cm (3-inch) wide center-mount
installation. See Figure 2-1 for mounting rail components. To prepare the mounting rails for flush-mount
installation in the two-post rack, perform the following steps:
1
Locate the two mounting rails and place them side by side on a smooth work surface, with the front
ends of the mounting rails toward you (see Figure 2-5).
2
Using a 3/8-inch wrench or nut driver, remove two nuts from the adjustable mounting bracket
(see Figure 2-5).
1
two-post open-frame rack
2
12-24 x 0.5-inch pan-head
Phillips screws (4 per rail)
3
center-mount mounting flange
2
mounting rails (2)
4
system rails (2)
6
release latch
2
1
4
6
3
5
Summary of Contents for PowerEdge 1950
Page 2: ......
Page 3: ...w w w d e l l c o m s u p p o r t d e l l c o m Rack Installation Guide ...
Page 28: ...26 Four Post Rack Installation ...
Page 40: ...38 Two Post Rack Installation ...
Page 42: ...40 Index 40 Index ...
Page 43: ...w w w d e l l c o m s u p p o r t d e l l c o m Guide d installation du rack ...
Page 80: ...78 Installation dans un rack à deux montants ...
Page 83: ...w w w d e l l c o m s u p p o r t d e l l c o m Rack Installationsanleitung ...
Page 123: ...w w w d e l l c o m s u p p o r t d e l l c o m ラック取り付けガイド ...
Page 134: ...132 4 柱型ラックの取り付け 図 1 4 垂直レールの印付け 1 垂直レールの印 2 1 ...
Page 160: ...158 2 柱型ラックの取り付け ...
Page 163: ...w w w d e l l c o m s u p p o r t d e l l c o m Guía de instalación del rack ...