Four-Post Rack Installation
23
Installing the Cable-Management Arm
NOTE:
You can attach the cable-management arm to either the right or left mounting rail, depending on how you
intend to route cables from the system.
1
If necessary, press the catch at the center of the cable-management arm retention latch on the tray,
and rotate the latch downwards (see Figure 1-12).
2
At the back of the system, fit the latch on the front end of the cable-management arm onto
the innermost bracket on the slide assembly, until the latch engages (see Figure 1-13).
3
Fit the latch on the unattached end of the cable-management arm onto the outermost bracket on
the slide assembly, until the latch engages (see Figure 1-13).
Figure 1-13.
Installing the Cable-Management Arm
1
mounting rails (2)
2
brackets (2)
3
latches (2)
4
cable-management arm
back of system
1
2
4
3
Summary of Contents for PowerEdge 1950
Page 2: ......
Page 3: ...w w w d e l l c o m s u p p o r t d e l l c o m Rack Installation Guide ...
Page 28: ...26 Four Post Rack Installation ...
Page 40: ...38 Two Post Rack Installation ...
Page 42: ...40 Index 40 Index ...
Page 43: ...w w w d e l l c o m s u p p o r t d e l l c o m Guide d installation du rack ...
Page 80: ...78 Installation dans un rack à deux montants ...
Page 83: ...w w w d e l l c o m s u p p o r t d e l l c o m Rack Installationsanleitung ...
Page 123: ...w w w d e l l c o m s u p p o r t d e l l c o m ラック取り付けガイド ...
Page 134: ...132 4 柱型ラックの取り付け 図 1 4 垂直レールの印付け 1 垂直レールの印 2 1 ...
Page 160: ...158 2 柱型ラックの取り付け ...
Page 163: ...w w w d e l l c o m s u p p o r t d e l l c o m Guía de instalación del rack ...