Installing the PDU front tray
Procedure
1. Locate the front PDU tray and fasteners.
2. Install the tray and secure it to the PDU support assembly with four (4) screws.
Figure 5 Installing the front PDU tray
1
2
1
3. Install two universal bezel clips in the bottom U of the 2U PDU space.
Installing rails for an EX300 rack
Install all rails for nodes and switches.
Install and secure rails in the following order:
1. Install all rails for EX300 nodes.
2. Secure all rails for EX300 nodes to the rack.
3. Install all rails for front and back-end switches.
4. Sucure all rails for front and back-end switches to the rack.
Do not install any nodes or switches until all rails are installed in the rack.
Install rails for EX300 nodes
Install all EX300 rails before you secure them to the rack.
The rails are labeled left and right, and cannot be interchanged. The front side of each
rail is labeled Left Front or Right Front when the rail faces the cabinet front.
Rail Installation
20
EX300
Third-Party Rack Installation Guide
Summary of Contents for ECS EX300
Page 1: ...ECS EX300 Third Party Rack Installation Guide 302 005 206 02 ...
Page 6: ...FIGURES 6 EX300 Third Party Rack Installation Guide ...
Page 7: ...Planning your lift 46 1 TABLES EX300 Third Party Rack Installation Guide 7 ...
Page 8: ...TABLES 8 EX300 Third Party Rack Installation Guide ...
Page 13: ...Third Party Rack Installation Overview Components for EX300 systems 13 ...
Page 14: ...Third Party Rack Installation Overview 14 EX300 Third Party Rack Installation Guide ...
Page 17: ...Figure 1 PDU component location Rail Installation Dell EMC PDU rail and component location 17 ...
Page 42: ...Bring the system online 42 EX300 Third Party Rack Installation Guide ...