Tension mode setup
10. For the last cabinet, release the bottom Locking pin at the
center rear Splay link slot of the cart.
11. Slightly lift the cart and disengage the Splay link.
12. Reinsert the Locking pin and lower the cart.
13. Lift the back of the cabinet until the Splay link has engaged.
14. Reinsert Locking pin
[2] (Safety pin).
15. Finally, lift the entire assembly to a height of approx. 30 cm
(1 ft) above ground.
16. With one person on each side, release the Locking pins at the
front of the cart.
17. Lower the cart, reinsert the Locking pins into their park
positions and put the cart aside.
For the attachment of further touring cart assemblies, proceed in
the same manner.
5. Check the assembly
Before hoisting the array to its operating position, recheck the
actual status of the entire assembly according to the checklist given
Chapter 7 "Safety and system checks" on page 38.
d&b XSL Rigging manual 1.1 en
- preliminary -
37