37
Commissioning
EN
RoCon UFH
6
Commissioning
6.1
Commissioning the product
Verify that the modules are properly connected.
Verify that the product is properly mounted to the DIN rail.
Apply mains voltage.
- The green LEDs for operation of the base module and the product light.
6.2
Wired system: Function test room controller
Verify that the room temperature is b15 °C and +25 °C.
1. Verify that the room controller to be tested is connected to the correct control cir-
cuit.
2. Set the room controller to be tested to +30 °C.
- The yellow LED lights up at the controller module to which the room temperature
controller is connected.
3. Repeat this procedure for all other room controllers.
6.3
Wireless system
(1)
: Connecting the room controller to the wire-
less controller module
6.3.1
Preparation
Verify that the single room temperature controller is in operation and that the
cover of the product has been removed.
Verify that the room controllers have been exposed to sunlight for at least one
day or that they have a battery.
Verify that the room controllers are close to the product.
Verify that the rear side of each of the room controllers are numbered consec-
utively and marked with the place of use. This helps to avoid subsequent con-
fusion.
Verify that a paper clip bent open and a ballpoint pen are available.
(1)
The wireless system is only available in certain sales areas.
Summary of Contents for RoCon UFH
Page 2: ......
Page 27: ...25 Mounting EN RoCon UFH 6 Refit the cover and close it Fig 5 5 Closing the cover ...
Page 64: ......
Page 126: ......
Page 151: ...25 Montage FR RoCon UFH 6 Accrocher le couvercle et le fermer Fig 5 5 Fermer le couvercle ...
Page 188: ......
Page 213: ...25 Montage NL RoCon UFH 6 Haak de afdekking vast en sluit haar Afb 5 5 Afdekking sluiten ...
Page 250: ......
Page 312: ...008 1706699 00 12 2020 Copyright Daikin www daikin eu ...