9
Service and maintenance
Installation and operating instructions
57
Gas Combi Unit
Floor-standing gas condensing boiler with integrated heat storage
008.1543899_02 – 04/2019 – EN
Fig. 9-7
Filling the heating system and storage tank charging cir-
cuit (shown on the GCU compact 5xx)
1
Filling hose with non-return valve (and pressure gauge)
(20)
)
2
Combined filling and draining valve
3
Heater ballcock - inflow
4
Heater ballcock - return flow
5.1
Valve drive
5.2
Unlocking key of the drive lock
6
Water tap
7
Automatic vent valve
8
Pressure gauge
3UV DHW
3-way distribution valve
3UVB1
3-way mixer valve
1
Connect the filling hose (
valve and an external pressure gauge
(20)
(on the building side)
to the fill/drain cock (
, item 2) and secure it against slip-
ping off with a hose clamp.
2
Make sure that the automatic vent valve cap is open (
,
item A).
Fig. 9-8
Undoing the automatic vent valve cap
A
Automatic vent valve cap
3
Open the water tap (
4
Open the fill/drain cock (
, item 2) and observe the pres-
sure gauge (
5
Fill the system with water until the pressure gauge shows that
the system target pressure is reached (
system 2 m
,
1 m water column corresponds to 0.1 bar).
The overpressure
valve must not actuate.
6
7
Vent the hydraulic block (see
8
9
valve from the fill/drain cock (
9.2.7
Venting the hydraulic block
1
Make sure that the automatic vent valve cap is open (
,
item A).
Fig. 9-9
Connecting the vent hose
B
Manual vent valve
2
Provide the manual vent valve (
, item B) with a hose and
direct it away from the device. Open the valve until water comes
out.
3
Switch on the power supply to the GCU compact.
(20)
if not already installed in the heating system
Summary of Contents for GCU compact Series
Page 2: ......