8
|
Piping installation
Installer reference guide
91
ERGA04~V3A+V37 + EHSH/X(B)04+08P30+50EF
Daikin Altherma 3 R ECH₂O
4P678716-1A – 2022.07
8 Piping installation
In this chapter
8.1 Preparing refrigerant piping
8.1.1 Refrigerant piping requirements
INFORMATION
Also read the precautions and requirements in the
Also see
"7.1.4 Special requirements for R32 units"
70] for additional
requirements.
▪
Piping length:
"7.1.3 Installation site requirements of the indoor unit"
▪
Piping material:
phosphoric acid deoxidised seamless copper
▪
Piping connections:
Only flare and brazed connections are allowed. The indoor
and outdoor units have flare connections. Connect both ends without brazing. If
brazing should be needed, take the guidelines in the outdoor unit installer
reference guide into account.
▪
Flare connections:
Only use annealed material.
▪
Piping diameter: