Manuale di Istruzione
Instruction Manual
23/08/2018
Rev.1 EN
98
5.2.5.1
Calibration verification
To verify the calibration, the unit should be left switched on for at least 15 minutes to
allow the thermal equilibrium of the electronic components. Then proceed as follows:
1.
Activate the
CALIBRATION MENU
by selecting the
CALIBRATION
option on
the
MAIN MENU
;
Fig. 5-15
2.
Correctly place the reference instrument (e.g. load cell) between the compression
platens of the test frame;
3.
When ready, turn ON the pump motor by acting on the relevant switch (note that the
pump motor switch is self-retaining when the mains electricity supply is connected);
in the meantime, set lever A up and lever B back on the flow control valve (rapid
approach phase); and the ram of the test machine will start to rise;
Fig. 5-16
A
B
Summary of Contents for WIZARD 2 50-C13A0X
Page 2: ......
Page 118: ...Manuale di Istruzione Instruction Manual 23 08 2018 Rev 1 EN 116 Note...
Page 119: ...Manuale di Istruzioni Instruction Manual Rev 1 EN 23 08 2018 117 Note...
Page 120: ......