Section 8. Operation
394
•
Where possible, run excitation leads and signal leads in separate shields
to minimize transients.
•
When measurement speed is not a prime consideration, additional time
can be used to ensure ample settling time. The settling time required
can be measured with the CR6.
•
In difficult cases, settling error can be measured as described in
Measuring Settling Time
(p. 394).
Measuring Settling Time
Settling time for a particular sensor and cable can be measured with the CR6.
Programming a series of measurements with increasing settling times will yield
data that indicate at what settling time a further increase results in negligible
change in the measured voltage. The programmed settling time at this point
indicates the settling time needed for the sensor / cable combination.
CRBasic example
Measuring Settling Time
(p. 394)
presents CRBasic code to help
determine settling time for a pressure transducer using a high-capacitance
semiconductor. The code consists of a series of full-bridge measurements
(
BrFull()
) with increasing settling times. The pressure transducer is placed in
steady-state conditions so changes in measured voltage are attributable to settling
time rather than changes in pressure. Reviewing
CRBasic Programming —
Details
(p. 180)
may help in understanding the CRBasic code in the example.
The first six measurements are shown in table
First Six Values of Settling Time
Data
(p. 395).
Each trace in figure
Settling Time for Pressure Transducer
(p. 395)
contains all twenty
PT()
mV/V values (left axis) for a given record number, along
with an average value showing the measurements as percent of final reading (right
axis). The reading has settled to 99.5% of the final value by the fourteenth
measurement, which is contained in variable PT(14). This is suitable accuracy
for the application, so a settling time of 1400 µs is determined to be adequate.
Measuring Settling Time
'This program example demonstrates the measurement of settling time using a single
'measurement instruction multiple times in succession. In this case, the program measures
'the temperature of the CR6 wiring panel.
Public
RefTemp
'Declare variable to receive instruction
BeginProg
Scan
(1,Sec,3,0)
PanelTemp
(RefTemp, 250)
'Instruction to make measurement
NextScan
EndProg
measures the settling time of a sensor measured with a differential
'voltage measurement
Public
PT(20)
'Variable to hold the measurements
DataTable
(Settle,True,100)
Sample
(20,PT(),IEEE4)
EndTable
Summary of Contents for CR6 Series
Page 2: ......
Page 4: ......
Page 6: ......
Page 32: ......
Page 36: ......
Page 38: ......
Page 76: ...Section 5 Overview 76 FIGURE 20 Half Bridge Wiring Example Wind Vane Potentiometer ...
Page 80: ...Section 5 Overview 80 FIGURE 23 Pulse Input Wiring Example Anemometer ...
Page 136: ......
Page 454: ...Section 8 Operation 454 FIGURE 104 Narrow Sweep High Noise ...
Page 459: ...Section 8 Operation 459 FIGURE 106 Vibrating Wire Sensor Calibration Report ...
Page 535: ...Section 8 Operation 535 8 11 2 Data Display FIGURE 121 CR1000KD Displaying Data ...
Page 537: ...Section 8 Operation 537 FIGURE 123 CR1000KD Real Time Custom ...
Page 538: ...Section 8 Operation 538 8 11 2 3 Final Storage Data FIGURE 124 CR1000KD Final Storage Data ...
Page 539: ...Section 8 Operation 539 8 11 3 Run Stop Program FIGURE 125 CR1000KD Run Stop Program ...
Page 541: ...Section 8 Operation 541 FIGURE 127 CR1000KD File Edit ...
Page 546: ......
Page 552: ......
Page 610: ...Section 11 Glossary 610 FIGURE 137 Relationships of Accuracy Precision and Resolution ...
Page 612: ......
Page 648: ......
Page 650: ......
Page 688: ......
Page 689: ......