It is recommended to install a concrete pad in order to maintain proper stability.
1. Lay out a concrete pad. Requires a minimum of 17"(length) x 24"(width) x 24"(20" depth below
ground, 4" above ground).
2. Install the electrical conduit. One
conduit is required for a single gate.
For double gates, add another
conduit. For underground loops,
add another conduit.
3. Pour the concrete pad.
4. Use 4 Wedge Anchors 1/2" to
secure the gate operator to the
concrete pad. Figure C
Above Ground 4"
Below Ground
Underground
depth may vary
due to local
building codes.
Reinforced
concrete
recommended.
20"
17"
Conduit
Gate
Operator
Slide Gate
Concrete Pad
17"
24"
4"
2"
Figure C
Wedge Anchor
1/2"
Step 2: Install the Concrete Pad
CAUTION
Call 811 for digging information or contact local underground utility locating companies
before digging more than 12 inches deep to avoid damaging underground power, gas,
or other utility lines.
9
Conduits should be
6-12" apart from one
another to avoid
interference