Order of the TwinSAFE groups
The order of the groups can be changed, in order to realize a defined processing sequence of the safety
application.
To this end, select the entry
Edit TwinSAFE Group Order
via the node menu of the safety project node. A
dialog opens, in which the order of the groups can be changed. The individual groups do not necessarily
have to be numbered in consecutive ascending order. The numbering can contain gaps.
Fig. 67: Context menu Edit TwinSAFE Group Order
The current group order is shown in the column
Current Value
. The new order is specified by entering a
value in the column
New Value,
followed by
OK
.
Fig. 68: Dialog Change Execution Order of TwinSAFE Groups
4.3.3.14
Command line
The
command line
below the SAL worksheet can be used to enter commands for executing functions.
Summary of Contents for EK1960 Series
Page 1: ...Operating Instructions for EK1960 TwinSAFE Compact Controller 1 3 1 2019 01 28 Version Date...
Page 2: ......
Page 6: ...Table of contents EK1960 6 Version 1 3 1...
Page 58: ...Operation EK1960 58 Version 1 3 1 Fig 51 Safety parameters of the input modules...
Page 140: ...Appendix EK1960 140 Version 1 3 1 5 2 Certificates...