May 22, 2023
EZ-SCREEN SLS Safety Light Curtain Instruction Manual
34
Level Surface
A
B
level
level
X
X
Mount the reset switch in a location that complies with the warning in
"Reset Switch Location" on page 25
Attach the required cordsets to the sensors, and route the sensor cables to the junction box, electrical panel, or other enclo-
sure in which the interface module, the redundant mechanically linked interposing relays, FSDs, or other safety-related parts
of the control system are located. This must be done per local wiring code for low-voltage dc control cables and may require
installation of electrical conduit. See
for selection of Banner supplied cables.
EZ-SCREEN SLS
is designed and manufactured to be highly resistant to electrical noise and to operate reliably in industrial
settings. However, extreme electrical noise may cause a random Trip or Latch condition; in extreme cases, a Lockout is pos-
sible.
Emitter and receiver wiring is low voltage; routing the sensor wires alongside power wires, motor/servo wires, or other high
voltage wiring may inject noise into the
EZ-SCREEN SLS
System. It is good wiring practice, and sometimes may be required
by code, to isolate emitter and receiver cables from high-voltage wires, avoid routing cables close to “noisy” wiring, and pro-
vide a good connection to earth ground.
Sensor cabling and any interconnect wiring should have an insulation temperature rating of at least 90 °C (194 °F). In addi-
tion, QD cabling and any interconnect wires should meet the specifications in the following table:
0.5 A
0.75 A
1.0 A
1.25 A
1.5 A
1.75 A
18 AWG
114.3 m (375 ft)
76.2 m (250 ft)
57.3 m (188 ft)
45.1 m (148 ft)
38.1 m (125 ft)
33.2 m (109 ft)
20 AWG
73.1 m (240 ft)
48.8 m (160 ft)
36.6 m (120 ft)
30.0 m (95 ft)
24.4 m (80 ft)
21.3 m (70 ft)
22 AWG
45.7 m (150 ft)
30.5 m (100 ft)
22.9 m (75 ft)
18.0 m (59 ft)
15.2 m (50 ft)
13.4 m (44 ft)
NOTE: Maximum cable lengths are intended to ensure that adequate power is available to the EZ-
SCREEN System when the supply is operating at +24 V DC – 15%.
For vertical installations
Figure 16.
Mounting the Reset Switch
5.5
Routing Cordsets
5.6
Maximum Machine Interface cable length versus total current draw (including both OSSD loads)
Table 3.
© Banner Engineering Corp.
Summary of Contents for EZ-SCREEN SLS
Page 16: ...May 22 2023 EZ SCREEN SLS Safety Light Curtain Instruction Manual 16 Banner Engineering Corp...
Page 52: ...Blank page 52...
Page 68: ...Blank page 68...
Page 90: ...Blank page 90...
Page 102: ...Blank page 102...
Page 106: ...Blank page 106...
Page 114: ...LinkedIn Twitter Facebook 2023 All rights reserved www bannerengineering com...