NOTE:
If jamb seals are being fitted they should be cut 100mm taller than the door height and fitted prior to fitting the vertical tracks.
Refer to Figure 2.8.2 for correct position. The fixing points should be spaced at 300-400mm centres.
Set the vertical tracks parallel on both sides of the door. Use the level/datum marks to ensure the tracks are level with each other or
the door will not function correctly. Ensure the detail at Figure 2.8.2 is followed. The set out measurements for b&D Storm-Shield
™
pFI are the same as pFT but take note of the positioning for the jamb spacer as they must be fitted under the jamb bracket with the
rolled edge facing you, as indicated at Figure 2.8.2. Once satisfied temporarily fix in position with at least two fixings to the top bracket
and one to the bottom track bracket, these will hold the tracks in position and allow for minor adjustment. All fixings with washers will
be fitted after the door is fully adjusted and operating satisfactorily. (For b&D Storm-Shield
™
pFI doors refer to the DTCM compliance
instructions). Ensure the b&D Storm-Shield
™
pinch point warning stickers are fitted correctly as previously indicated.
FIGURE 2.8.2 WHEEL-AxLE
A
B
C
E/
F
D
A
C
B
E/
F
A
B
C
E/
F
D
A
C
B
E/
F
PFT & B&D STORM-SHIELD
™
PFI
PFI
FIGURE 2.8.1 INSTALLING VERTICAL TRACKS
NOTE:
The DTCM compliance fixing
details for b&D Storm-Shield
™
pFI
vertical tracks must be followed
however the initial set out is the same.
NOTE:
There must
be at least 3 fixings
with washers to each
top bracket and other
fixings are to have
washers fitted.
Tracks shown are
indicative only.
FINAL B&D STORM-SHIELD
™
PFI
WITH TRACKLOCK POSITIONING
10
10
30
8
TRACK
A
C
B
E/F
2.8 INSTALLING vERTICAL TRACKS
17
panelift
®
pFT, panelift
®
Icon
™
pFI, b&D Storm-Shield
™
pFI and Insul-Shield
™
Installation Instructions
Revision 9 - March 2016