80 / 80
12.5. OCS 500N6 1-phase operating with 3-phase devices
A 3-phase OCS 500 N6 uses in single phase mode the following phases:
L1
= phase line L
N
= neutral line N
PE
= protected earth PE
L+N-PE coupling
For coupling L+N-PE
select L1+L2+L3+N-PE
The lines L2 and L3 are not connected in the OCS 500 N6
and therefore the pulse is coupled only to the connected
lines L and N to PE
Using software iec.control
Some standards and the DC coupling selection do not offer the coupling L+N-PE. For test this coupling precedes
the following steps:
Figure 11.1: Coupling L+N-PE with software IEC.control
Example for select coupling L+N-PE
1.
DoubleClick into the area
Standard Area
for change to
Device Area
mode
2.
Select
Ringwave
3.
Select radio button
4 Line + PE
coupling. This offers the desired coupling mode
4.
Select the button
coupling
for open the coupling selection
5.
Select coupling
L1+L2+L3+N-PE
and deselect all other couplings
6.
Press
OK
button
Save the setting as test file for use it later or in a link file.