SW1000 Installation and Operation Instructions
Page 14
For Assistance: [email protected] +1 (909) 591-8431 PUD3448R2-1
1. Route primary power and access control wiring
through the base plate into the tower assembly
[Figure 10].
2. Align the tower assembly and base plate with
the anchor holes. Insert four (4) anchor bolts and
washers [Figure 11].
3. Using a torque wrench and 9/16" socket, torque the
anchor bolts to 20 ft-lbs.
4. Using a level, verify the tower is plumb and level. If
necessary, use shims to level the tower.
5. Apply a bead of clear RTV silicone around the base
plate.
If installing an SW1000T tandem gate, refer to
Appendix A for instructions on routing DC power and
communication to the slave gate.
NOTE
Route Wiring
Figure 10
Anchor the Tower
Assembly
Figure 11
Tower Assembly Installation