34
Installation and Verification Manual
2
Installation (Getting Started)
Preparation
Initial Inspection
Inspect the shipping container for damage.
If the shipping container or cushioning material is damaged, it
should be kept until the contents of the shipment have been
checked for completeness and the instrument has been checked
both mechanically and electrically.
For procedures for checking operation on delivery See
“Operation Checks on Delivery"
If the contents of the shipment are incomplete, if there is
mechanical damage or defect, notify the nearest Agilent Office.
If the instrument does not pass the delivery checks given (See
“Operation Checks on Delivery"
on page 41.) notify the nearest
Agilent office.
If the shipping container is also damaged, or the cushioning
material shows signs of stress, notify the carrier as well as the
nearest Agilent office. Keep the shipping materials for the
carrier’s inspection. The Agilent office will arrange for repair or
replacement without waiting for claim settlement.
Operating Environment
DO NOT
operate the product in an explosive atmosphere or in
the presence of flammable gasses or fumes.
This instrument may be operated in environments within the
following limits:
Temperature:
0 to +40 degC (option 004); 0 to +45 degC (option
005).
WA R N I N G
To avoid hazardous electrical shock, do not perform electrical tests
when there are signs of shipping damage to any portion of the outer
enclosure.
panther3_iv.book Page 34 Wednesday, January 15, 2003 12:03 PM